River Intake Pump Station Almost Complete!

From their newsletter:

“River Intake Pump Station (RIPS) – almost complete!
The roof is now complete! Fish screens will be installed next week. Concrete will also be poured for the new RIPS pedestrian gate.
Crews have finished removing the work decking around the exterior of the structure, and have started removing the work bridge. The large red crane will be removed from the site in early February.
Startup for pump testing and commissioning is expected to begin in late January and continue through February.
Check out this drone’s eye view of construction at the RIPS during fall, along with other key facilities. “

River Intake Pump Station

River Intake Pump Station

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s